PROJECTS

 

Sl. Project Description
1 Airport Project, with Zahran Operation and Maintenance
  • Primary Injection Testing of LV Breakers.
  • Secondary Injection Testing of MV Protective relays.
  • Infra-red thermo graphic inspection of RMUs, LV Breakers, MV/LV bus-bars
  • Calibration of Electrical Analog Panel Meters.
2

KKMC, Hafar Al Batin

Testing and commissioning of new sub-station.
  • Step-up Transformer 13.8 / 33 kV, 40 MVA.
  • MV Switchgear, along with SF6 breakers.
  • Auxiliary transformer 1000 kVA, 630 kVA
  • Protection relays.
  • Contact resistance.
  • Primary injection test of breakers
3 Petro Rabigh Testing & Commissioning of GUTOR (Sweden) UPS Capacity 50kVA
4 Le Meridien Al Hada (Taif)
  • Infra-red Thermo graphic inspection of all electrical distribution panels.
  • Installation of Fire Fighting Water pipe line along with Fire Hose Cabinets and 8” dia Pressure Reducing Valve (PRV).
  • Installation of grounding system for central PABX
5 National Water Company
  • Replaced a Ring Main Unit (RMU) at Sewage Treatment Plant Al Ruwais.
  • Replaced Oil in 2500 kVA distribution Transformer.
6 Tabuk, Al Wedjh, Hail and Al Ula airports.
  • Testing of LV main breakers of all distribution sub-stations.
  • Transformer Turn Ratio Testing of all distribution transformers

 

---